CITY of RAPID CITY Agenda Item Summary |
||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||
Public Works Committee Meeting Date: 2/24/2015 |
City Council Meeting Date: 3/2/2015 |
|||||||||||||||||||||||||||
Staff Contact: Dan Coon |
Petitioner: |
|||||||||||||||||||||||||||
Location: Dyess Avenue |
|
|||||||||||||||||||||||||||
Agenda Title: |
||||||||||||||||||||||||||||
Authorize lowering the percentage of work that the Contractor must perform, with their own organization, from 50% to 35% for the Ellsworth Air Force Base Water Meter Facility Relocation, Project No. W11-1936. |
||||||||||||||||||||||||||||
Summary: |
||||||||||||||||||||||||||||
Revise Paragraph 7.40 of Section 7 - General Conditions of the City of Rapid City Standard Specifications to allow the Contractor to perform not less than 35% of the work with his own organization instead of the standard 50% for the Ellsworth Air Force Base Water Meter Facility Relocation project. |
||||||||||||||||||||||||||||
Funding Source & Fiscal Impact (if applicable): |
||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||
Recommendation: |
||||||||||||||||||||||||||||
Action: Approve Notes: |
||||||||||||||||||||||||||||
City Council Options: |
||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||
Attachments & Links: |
||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||